Footing / Forms
Must be inspected after all footing formwork is in place, but prior to pouring of concrete.
Foundation (prior to backfill)
Must be inspected after it has been constructed, anchor bolts in place, damp proofing or waterproofing has been applied, drainage layer has been installed and drainage tile and granular covers are in place.
Framing / Mechanical Rough-in
The building superstructure must be inspected after framing members and roof, floor, and wall sheathing are in place, and all mechanical ventilation and plumbing is roughed in, but prior to application of any interior finishes. If truss drawings were not submitted at the time of application, they are a requirement before this inspection can be completed.
Air Barrier
Substantial completion of exterior air barrier system prior to installing exterior finish
Insulation and Vapour Barrier
Must be inspected after all required insulation and vapour barriers are in place, but prior to the application of any interior finish
Fire Separation and Closures
In the case of plaster, the inspection must be completed after all lath and reinforcement for corners and openings are in place, but prior to application of the first coat of plaster. In the case of drywall, the inspection must be completed after all drywall is in place, but prior to the application of any drywall compound to the joints or nail screw holes. Fire stopping shall be installed in accordance with the shop drawing as provided. Fire protection systems include standpipe, sprinkler, fire alarm, and emergency lighting systems
Occupancy Permit
If the building is to be occupied prior to the final inspection being completed, and an Occupancy Permit must be obtained. In order to obtain an Occupancy Permit, the provisions of articles OBC Div C 1.3.3.1, 1.3.3.2 or 1.3.3.4, or 1.3.3.5 as amended, must be complied with and the final lot grading certificate must be submitted. Failure to obtain an Occupancy Permit under these circumstances may result in legal action being taken.
Final
This inspection is completed after all requirements of the Ontario Building Code have been fulfilled. For final inspection, provide hydro and plumbing final inspections, a survey showing the location of the building on the lot as built, if required. Also, provide the date of completion of the building and the final lot grading certificate. Final inspection cannot be carried out until the building is complete and ready for occupancy.