Port Dover Water Treatment Plant – Phase 2 Upgrades

Project Construction Budget

  • $7,147,388.63

Proposed Start Date

  • June 2023

Estimated Completion Date

  • December 2024

It is our intention to minimize the impact of this vital infrastructure work on the public. If you have any questions or concerns regarding the work being completed, please contact the appropriate individual shown above.

Project Description

H2Ontario Inc. has been awarded the Phase 2 Upgrades at the Port Dover Water Treatment Plant, located at 603 Nelson Street West in Port Dover.

The work will consist of upgrades to the main treatment processes, tankage and pumping within the existing building structures, replacement of the emergency generator, construction of a new wastewater holding tank, site piping, and restoration work.

The Water Treatment Plant site has been under construction for the previous couple of years, and this final phase of construction will complete the project, ensuring an increased capacity and a reliable water supply to the town of Port Dover. Generally, the public will not be affected by this construction; however, the ongoing construction traffic and site work require limited access to the plant premises. For public and workers’ safety reasons, we recommend accessing the beach at nearby locations until the work is completed.

Contacts

The following is a list of contacts for the project:

Norfolk County

Project Manager
Shubham Jindal
(519) 426-5870, extension 1141
shubham.jindal@norfolkcounty.ca

Contractor
H2Ontario Inc.
Sean Parsons
(519) 662-1134
sparsons@h2ontario.com

Consultant
WSP
Gino Giancola, CET, PMP
(905) 321-3975
gino.giancola@wsp.com

After-hours emergency 1-877-298-5888