Project Construction Budget

$7,147,388.63

Proposed Start Date

June 2023

Estimated Completion Date

December 2024

It is our intention to minimize the impact of this vital infrastructure work on the public.  If you have any questions or concerns regarding the work being completed, please contact the appropriate individual shown above.

Project Description

The Phase 2 Upgrades at the Port Dover Water Treatment Plant located at 603 Nelson Street West in Port Dover has been awarded to H2Ontario Inc.

The work will consist of upgrades to the main treatment processes, tankage and pumping within the existing building structures, replacement of the emergency generator, construction of a new wastewater holding tank, site piping and restoration work.

The Water Treatment Plant site has been under construction for the previous couple of years, and this final phase of construction will complete the project, ensuring an increased capacity and a reliable water supply to the town of Port Dover.  Generally, the public will not be affected by this construction, however, the on-going construction traffic and site work require limited access to the plant premises. For public and workers’ safety reasons we recommend accessing the beach at nearby locations until the work is completed.

Contacts


Contractor
H2Ontario Inc.
Sean Parsons
(519) 662-1134
[email protected]

Consultant
WSP
Gino Giancola, CET, PMP
(905) 321-3975
[email protected]

Norfolk County
Project Manager
Shubham Jindal
(519) 426-5870 ext. 1141
[email protected]

 