Drinking water will be supplied to Simcoe through a new transmission main and a booster pumping station connected to the Townsend-Haldimand drinking water system and to the future Waterford interconnection.
A new elevated tank will be built on the northwest side of Simcoe to meet the fire protection requirements and connect to the Delhi-Courtland system. The booster pumping station will be designed to accommodate the future pumps required for Waterford and Delhi-Courtland.
A metering chamber will be built at the boundary between the two counties to monitor and record the flows consumed by Norfolk County through the Simcoe Connection.
Phase 1 – Townsend-Simcoe Water Supply System Progress
Phase 1 projects:
- Project 1: Townsend-Simcoe Transmission Watermain: 90% design in progress
- Project 2: Simcoe Booster Pumping Station: 90% design in progress
- Project 3: New Simcoe Elevated Tank: 90% design in progress
- Project 4: Nanticoke Water Treatment Plant Upgrade Phase 1: Pre-design in progress
Phase 1 updates:
July 2024
- Project 4 – Nanticoke Treatment Plant upgrades pre-design complete
- 90% detailed design for Projects 1-3 nearing completion
April 2024
- 60% detailed design for Projects 1-3 complete
February 2024
- Geotechnical investigations for Phase 1 Townsend-Simcoe completed
- Hydraulic modelling and transient analysis report updated for 2051 requirements and complete
- Design progressed to the 60% stage based on confirmed hydraulic conditions
January 2024
- Phase 1 Nanticoke Water Treatment Plant Upgrade project was awarded and kicked off
December 2023
- Phase 1 Townsend-Simcoe System design was reviewed and updated to ensure that the planned water demand projections to 2051 in terms of hydraulic capacity, fire protection and pressure requirements.
May 2023
- Class Environmental Assessment filed with the Ministry of Environment, Conservation and Parks and process complete. Read more on EngageNorfolk.
April 2023
- Notice of completion: This Study was conducted following the requirements for Schedule ‘B’ projects within the Municipal Class EA document (as amended in 2015) under the Ontario Environmental Assessment Act. Read more on EngageNorfolk.
November 2022
- The Second Public Information Centre was held on November 8, 2022, from 5:00 to 7:00 p.m. Watch the session recording and read more.
August 2022
- Public Information Centre (PIC) held to present background information on the study. Watch the session and read the documents shared.
July 2022
- Municipal Class Environmental Assessment (EA) was initiated to implement an approximately 20 km transmission water main connecting Simcoe to the Townsend Water Supply System to secure water supply from the Nanticoke Water Treatment Plant, including a new elevated water tank and booster station. These improvements are required to meet long-term (2041) Inter-Urban Water Supply capacity and quality demands within the County. Read more.
May 2022
- Engineering for Phase 1 – Townsend-Simcoe Interconnection started.
- Class Environmental Assessment Schedule B and Preliminary Design commenced.